Capital Projects/Facilities

Jefferson Elementary School: Renovation Update
July 8, 2026

Jefferson County Schools continues to make steady progress on the Jefferson Elementary School renovation project.
Initial preparation work for asbestos abatement began on June 8, with the removal of asbestos-containing materials officially starting on June 15. As of July 8, the abatement contractor has completed approximately 70% of the asbestos removal process.
Throughout the project, independent air clearance testing has been conducted as work is completed in each area. To date, all air clearance tests have returned clear results, demonstrating that the contractor is performing the work safely, thoroughly, and in accordance with all state and federal environmental regulations. These results also reflect the exceptional care being taken to properly remove asbestos-containing materials and meticulously clean each area before it is cleared for the next phase of construction.
Before any Jefferson County Schools staff or students are permitted to re-enter the building, the contractor must successfully complete the entire abatement process and the building must pass all final independent air clearance testing. These final clearances are required to verify that the building is safe for occupancy and that all asbestos-containing materials have been properly removed.
Based on the current pace of work, we are optimistic that final clearances will be achieved and Jefferson County Schools will regain access to the building between July 17 and July 24. Once access is restored, additional work associated with the renovation project will continue as scheduled. A painting contractor is scheduled to begin next week, painting classroom walls where lockers and cabinets were removed.
We appreciate the professionalism and diligence of the abatement contractor and the environmental consultants who continue to monitor the project. Their commitment to safety ensures that this work is completed correctly and that the health and safety of our students, staff, and community remain our highest priority.
Jefferson County Schools remains committed to keeping our community informed as this important renovation project progresses. Additional updates will be provided as the abatement phase nears completion and the project advances into the next stage of construction.

Archives: Capital Project Updates
- Talbott Elementary: July 6, 2026
- Talbott Elementary: June 26, 2026
- Jefferson Elementary: June 22, 2026
- Talbott Elementary: June 16, 2026
- Talbott Elementary: June 1, 2026
- Talbott Elementary: May 27, 2026





